SUTTON LOCK WALKWAY REPLACEMENT

Work is to be undertaken in two phases so that one side remains accessible. Phase one is to replace the East side walkway with work commencing on Monday 3rd November and expected to complete by Saturday 8th November. Phase two is to replace the West side walkway with work programmed to start on Monday 24th November and completion by Saturday 29th November.

During these periods there will be disruption to our normal locking procedure whilst driving or lifting operations are in progress. Disruption will be of course kept to a minimum and we will keep berth holders informed by an advisory email. Should you require passage through the lock during these periods of work please contact the duty lock keeper on 01752 204732 to ensure passage is possible at the time you require.